Solution ID: prim5679 |
Error: "Process completed with errors. See log file for details." when saving a project using ProjectLink |
Status: Reviewed |
Version(s): 4.0 |
Problem: | When saving a project using the ProjectLink, I am receiving an error message. The error message is Process completed with errors. See log file for details. When I open Project Manager, the project select in ProjectLink has not been saved. ![]() |
Problem: | The log file contains the following information: INFORMATION: Process Started: 04-09-2004 16:10:55 INFORMATION: Template: New |
Cause: | This error is caused by selecting the Resource Name to be imported as the Resource ID. The Resource ID in Project Manager is a maximum of 20 characters. The resource name in Microsoft Project can be longer than 20 characters. In Microsoft Project, if the first 20 characters of two or more resources are the same, ProjectLink will not be able to import the project. |
Fix: | To resolve this: 1. Open Microsoft Project. |