Solution ID: prim24070 |
Is it possible to assign suspend/resume dates to several activities at once? |
Status: Reviewed |
Version(s): 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1 |
Problem: | Sample Global Change: Adding Suspend and Resume dates to multiple activities. |
Problem: | Is it possible to assign suspend and resume dates to several activities at once? |
Fix: | Execute the following Global change to assign Suspend and Resume date to multiple activities. Note: If the Suspend or Resume dates can not be applied, a warning message will be displayed in the Global Change report. Suspend dates will not be applied to activities with Activity percent complete must be greater than zero. In this example, the Suspend date on activity A1260 could not be applied because the activity does not have an Actual Start. The Resume date could not be applied because there was no Suspend date. Primavera Global Change: Assign Suspend and Resume dates Activity ID Field Old Value New Value A1260 Suspend Date |