Solution ID: prim12591 |
When grouping by resources, activities with cost accounts lose their target bars. |
Status: Reviewed |
Version(s): 3.1 |
Fact: | The cost accounts and resources on the activities in both the current and target project are the same. |
Fact: | When you make a copy of the current schedule, and make it the target of the current schedule, the bars appear. |
Problem: | When grouping by resources, activities with cost accounts lose their target bars. |
Fix: | The cost account dictionaries are different from the current to the target schedule. Transfer the cost account dictionary from the current schedule to the target schedule. 1. In the target schedule, go to Data, Cost Accounts. 2. Click Transfer, then click OK at the warning. 3. Choose the current schedule to transfer from, then click Transfer. The target bars should now appear in the current schedule. |